I realized I was getting used to doing work out here when writing dates with the day first became a natural thing to do.
-
As my colleague, Luke, once said, "Ladies and Gentlemen, we live in a material world."
I couldn't agree more. I spent the last few days learning the ins and outs of
studbolts. Possibly the most boring of all topics. A
studbolt is a threaded metal rod - like a screw except without the head. We use it all over the place as a means of fastening flanged piping and valves/instruments together. We didn't order all the different kind of
studbolts we needed so I've been scrounging our database for anything available. Things I learned about
studbolts:
1. You can always use a longer
studbolt. If it's over 20mm past the desired length you can cut it down to size. (The usual rule is two threads past the nut)
2. If you do end up cutting the end off the
studbolt, you need to paint the tip, grease it up or cap it with a plastic cap to prevent corrosion. (Well, this is mostly true for our case where we purchased galvanized
studbolts).
I got an e-mail about 15 minutes ago that I think really encapsulates the Company-Contractor relationship that energy companies have with engineering contractors. While going through our purchase orders I noticed that we had ordered 5 circuit breakers - 2 with trip units installed in them and 3 without. We had also ordered 3 trip units separately. Well, it turns out the 3 separate trip units never got ordered and so we don't have them. I'm not an electrical engineer (in my book electricity = magic), so I shot an e-mail to my Project Engineer to find out if we needed the 3 trip units. He passed the question onto our contractor who told me the following:
1. They originally wanted to purchase all 5 trip units separately from the circuit breakers.
2. They found out that the trip units could not be purchased separately from the circuit breakers.
3. We need to install 3 trip units inside the circuit breakers without trip units.
4. His proposed solution, I kid you not, is to purchase the 3 trip units separately (read step 2 if you don't find this immediately ironic).
Since this happened at the end of the day, I found it more humorous than disconcerting.
Other than that, I've realized the monetary impact of poor communication. My national operations rep and I couldn't get the distinction between a Work Request and a Work Order straightened out. I'll remember to ask for definitions in the future. Cost implication = over 3 grand. What a waste.
In closing, the weather has become absolutely amazing. It's slightly chilly in the morning and sunny and bright during the day. Everyone and everything is loving the weather (including the
mosquitoes). There's grass growing, all kinds of birds (saw my first gull going towards the Caspian this morning) and it's bright until well past 9PM.